1:15 - Paul is the customer.
1:20 - Paul wants use to complete 4 user stories.
1:25 - Paul's suggestions
*Search suggestions
-Paul's priority: 2
-Estimated Time: 2 hrs
-Velocity Time: 6.25 hrs
*GET RESULTS
-Paul's priority: 1
-Estimated Time: 2 hrs
-Velocity Time: 6.25hrs
*User submissions
-Paul's priority: 3
-Estimated Time: 6 hrs
-Velocity Time: 18.75 hrs
*Favorites lists
-Paul's priority: 4
-Estimated Time: 8 hrs
-Velocity Time: 25 hrs
*Shortest walking route
-Paul's priority: 6
-Estimated Time: 40 hrs
-Velocity Time: 125 hrs
*Turn by turn walking directions
-Paul's priority: 5
-Estimated Time: 40 hrs
-Velocity Time: 125 hrs
*See buildings that are within 100 yards of your current position
-Paul's priority: 8
-Estimated Time: 60 hrs
-Velocity Time: 187.5 hrs
*User submitted photos
-Paul's priority: 7
-Estimated Time: 50 hrs
-Velocity Time: 156.25 hrs
Average Velocity: 3.125
1:30 - Paul's suggestions that he approved for this iterations
*Search suggestions
*GET RESULTS
*User submissions
*Favorites lists